Following a reopening of the passage between Donegall Place and Royal Avenue, the Belfast City Planning group have reported increased footfall in a recent City Recovery update

Outline schedule of work

The restoration of the walkway at Castle St and roadway at Castle junction are projected to be in place by Spring 2019.

Primark shipping container retention scheme

Now that the container retention scheme is in place the project will proceed as follows:

  1. Interior of building to be removed safely
  2. New building structure to be built
  3. Historic facade to be attached to new interior structure
  4. Stabalising containers to be removed.

It is projected to take approximately 2-3 years to complete.

 

Post fire footfall figures

 

 